The 4D Construction Learning Environment project began work in February 2014 with completion planned for January 2016. The project team envisioned four 6-monthly phases over the project life focused on developing, pilotting, trialling and evaluating the planned learning and teaching resources. The main activities can be summarised as:
The project timeline is detailed in the table below..
Key Activities | Due | Status |
---|---|---|
Year 1 Tasks: 1/02/2014/- 31/01/2015 | ||
Establish project | March | Complete |
Consolidate Literature review | May | Complete |
Establish website | May | Complete |
Ethical clearance | June | Complete |
Develop pilot 4D learning environment | June | Online July 2015 |
Develop scenarios (workshops) | June | Complete |
Consolidate scenarios (learning activities and 4D walk-throughs | July | Complete |
Draft curriculum (learning activity) outline | June 2014 | Complete |
Team meetings (teleconference) | monthly | Complete |
Team face-to-face | 2 days in July | Complete |
Advisory group meeting | April & November 2014 | update 11/11/14 |
1st Progress report due | 31/07/2014 | Delivered |
Test pilot 4D learning environment | October 2014 | Complete |
Develop trial 4D learning environment | January 2015 | Complete |
Consolidate trial learning activities | January 2015 | Complete |
Maintain website | February 2016 | Complete |
Scenario writing workshop | December 2014 | 27/01/2015 |
Face to face team meeting | January 2015 | 28/01/2015 |
Project progress evaluation | January 2015 | Complete |
Year 1 interim report due | 31/01/2015 | Delivered |
Year 2 tasks: 1/02/2015-31/01/2016 | ||
Trial 4D environment and learning activities at all partner institutions | re-planned: UniSA & UoN s1, 2015; UoN & UQ s2, 2015 | Complete |
Interview key professional informants | March-July | Complete |
Evaluate trials | July and Nov 2015 | Complete |
Advisory group meeting | April 2015 |
update 31/08/2015 |
Face-to-face team meeting | replanned to 13-14 July 2015 | Complete |
2nd Progress report due | 31/07/2015 | 4/08/2015 |
Edit 4D learning environment | October 2015 | Complete Jan 2016 |
Advisory group meeting | 26 November 2015 | Complete |
Collation and production of final resources | December 2015 | in progress |
Evaluation report | December 2015 | Delivered |
Face-to-face team meeting | 14-15 December 2015 | Complete |
Final project report due | 30/01/2016 | Delivered 16/02/2016 |
Financial acquittal report due | 30/03/2016 |